Construction Scheduling Software 2026: Picks and Published Prices

17 min read

Disclosure: Augmented Trades participates in affiliate programs. If you click a link and make a purchase we may earn a commission at no additional cost to you. Read our full disclosure.

Short answer: for a small GC or remodeler who wants construction scheduling software built for contractors, the lowest published price for a full project schedule built in the app (Gantt chart, task dependencies, critical path and baselines) is Contractor Foreman’s Plus plan: $166 a month billed annually for up to 8 users. A general tool, Microsoft Planner and Project Plan 3 ($30 per user a month, paid yearly), has the same four features and costs less below 6 users, but has no estimates, sub portal or job costing. Buildertrend lists a full scheduling set plus weather overlays, offline mobile and change-order links, but only quotes its price. Commercial GCs who build schedules in P6 or Microsoft Project should look at Procore or Autodesk Forma Build. If you only need a Gantt chart, Microsoft Planner Plan 1 ($10 per user a month, paid yearly) and Smartsheet Pro ($9 per member a month, billed yearly) cost the least, and Fieldwire has a free plan for 5 users. Filling crew calendars day by day is a different job, handled by crew schedulers like Connecteam.

Prices and features as of November 22, 2026, read from each vendor’s own pages on the dates in the table. Projul and Contractor Foreman are affiliates; the picks follow from the check below, not from that.

Project schedules vs crew scheduling: which one you need

“Construction scheduling software” covers two different jobs, and most lists mix them up.

  • Project schedules plan a whole job from demo to punch list. It needs a Gantt chart, dependencies (when framing slips, drywall moves with it), a critical path (CPM) showing which tasks drive the finish date, and a baseline to compare plan with reality. Bigger jobs add lookahead and pull planning sessions with the trades. GCs, remodelers and builders need this.
  • Crew or day scheduling decides who goes where tomorrow. It needs a calendar of people, phone alerts and a view of who is overbooked. Specialty crews and service trades need this.

This page compares scheduling software for construction project schedules, with crew tools rated alongside. If you want construction management scheduling software that also runs budgets, change orders and daily logs, not just the schedule, see our project management software for general contractors guide. If your work is mostly same-day service calls, see our guide to scheduling software for contractors. For dispatch boards and technician routing, see field service dispatch software.

Construction scheduling software at a glance

How we rate: a “Strong” project schedule has Gantt, dependencies, critical path and baselines on the vendor’s page; “Good” has Gantt plus some of those; “Basic” is a Gantt or calendar view only. “Strong” crew scheduling means a crew board or crew-load view with alerts.

SoftwareProject scheduleCrew/day schedulingBest forPublished starting pricePrice checked
Contractor ForemanStrong: Gantt, dependencies, CPM, baselinesGood: Crew ScheduleSmall GCs and remodelersPlus $166/mo billed annually, 8 usersNov 22, 2026
BuildertrendStrong: Gantt, dependencies, critical path, baselinesBasic: sub sharing and alertsResidential builders, 5+ projects a yearQuote; unlimited usersNov 22, 2026
ProcoreStrong: Gantt, critical path, dependencies, baselines, P6 importGood: tasks to crews and subsCommercial GCsQuote, by construction volumeNov 22, 2026
Autodesk Forma BuildStrong for imported schedulesBasic: weekly work plansCommercial GCs using P6 or MS Project$67–$117/user/mo, paid annuallyNov 20, 2026
ProjulGood on Core+: Gantt, dependenciesStrong: crew-load heat mapSmall residential crewsStarter $199/mo annually; Gantt from Core+ $599/moNov 22, 2026
JobTreadBasic: Gantt, calendar, listGood: capacity view, free crew usersResidential GCs and remodelers$159/mo annually or $199 monthly, 1 userNov 22, 2026
Houzz ProGood: Gantt, dependencies, baselines (Advanced)Basic: sub task accessRemodelers and design-buildPro $199/mo, 1 user, annual termNov 22, 2026
FieldwireBasic: Gantt (plan unconfirmed), lookaheadGood: dispatch to trades and foremenField teams and specialty subsFree for 5 users; Pro $39/user/mo annuallyNov 20, 2026
Microsoft Planner and ProjectGood on Plan 1; Strong on Plan 3Basic: People (workload) view on Plan 1MS Project users$10–$30/user/mo, paid yearlyNov 22, 2026
SmartsheetGood on Pro; baselines on BusinessBasic: workload tracking on BusinessOffice schedules with many viewersPro $9/member/mo yearlyNov 22, 2026
monday.comBasic on Standard; dependencies on ProNoneTeams already on monday.comStandard $12/seat/mo yearly, 3 seats min.Nov 22, 2026
ConnecteamNoneStrong on Advanced: shifts and templatesCrew and shift schedulingFree to 10 users; Basic $29/mo, Advanced $49/mo for 30, yearlyNov 22, 2026
Crew ConsoleNoneGood: jobs, crews, equipmentDaily crew and equipment$7/person/mo for schedulingNov 22, 2026

The best construction scheduling software in 2026

Contractor Foreman: a full schedule at a published flat price

Contractor Foreman‘s scheduling page describes a Gantt scheduler where “all dependent tasks are automatically adjusted” when you move one, CPM to find the tasks that drive your completion date, baselines, templates, and Microsoft Project import and export.

The catch: its plan grid ticks Scheduling and Crew Schedule only on Plus and up: $166 a month billed annually or $199 monthly, for up to 8 users. Basic ($49) and Standard ($105) don’t include it, and the client portal starts on Pro ($221 annual, 15 users). There’s a 30-day free trial and a 100-day money-back guarantee on annual Plus and up.

Buildertrend: full scheduler plus weather overlays and offline mode, priced by quote

Buildertrend‘s schedule page lists Gantt charts with predecessors and dependencies, critical path scheduling, baselines, templates, and weather and holiday overlays. Change orders update the schedule, subs and clients see it “by item or phase” through portals, and the mobile app works offline.

The catch: no published price. The pricing page offers unlimited users and 10% off annual plans paid upfront, and its quote form targets builders who oversee 5 or more projects a year. See our Buildertrend alternatives if the quote comes back high.

Procore: for commercial GCs running imported schedules

Procore imports P6 or MS Project schedules (or builds them from scratch), keeps them synced, and lets you “monitor the critical path,” run lookaheads, and assign tasks to crews and subcontractors. Delays can be traced to RFIs.

The catch: pricing is an upfront annual fee by product, based on your annual construction volume. Users are unlimited, including subs and clients. Our Procore alternatives page covers cheaper options.

Autodesk Forma Build: version compare for big schedules

Autodesk Forma Build (formerly Autodesk Build) shows schedules in a list-and-Gantt view you can sort by critical status. You can compare up to 5 schedule versions, link the schedule to cost, run weekly work plans, and view it on mobile. Baselines show when the imported file has them.

The catch: the pages we read describe schedules imported from “traditional schedule authoring software.” They don’t confirm native schedule building or say which tier includes Schedule. Prices (November 20, 2026): Essentials $67 and Forma Build $117 per user a month, paid annually.

Projul: strong crew view, Gantt on the higher plans

Projul‘s schedule page offers drag-and-drop scheduling, 7 schedule views, a heat-mapped view of overloaded crews, dependencies that shift when a predecessor slips, and “project sliding” to push a section by set days. Subs see only their own tasks, and you can see who has acknowledged them.

The catch: Gantt charts, schedule conflicts, linear timelines and the client portal start on Core+: $599 a month billed annually ($799 monthly) for up to 20 users. Starter ($199 annual, 3 users) and Core ($399, 10 users) include scheduling and calendars only. Sub access isn’t on Starter (up to 20 subs on Core, unlimited from Core+), and the full mobile app starts on Core. No baseline or critical-path tool is described. Details in our Projul review and pricing.

JobTread: free logins for subs, clients and field crew

JobTread gives you calendar, Gantt and list views, task templates, and a way to “identify available capacity and bottleneck constraints.” Sub, vendor and customer portal users are free and unlimited, and field crew who only view schedules, check off tasks and upload photos can be free users too.

The catch: its pages don’t mention dependencies, critical path or baselines. It’s a web app, not in the app stores. Pricing is $159 a month billed annually or $199 monthly with one user, plus $16 to $20 per extra internal user. There’s no free trial, but monthly plans have a 30-day money-back guarantee. See JobTread pricing.

Houzz Pro: estimates that become schedules

Houzz Pro combines Gantt, calendar and list views, lets you drag connected phases together, and uses AI to turn an estimate into a schedule. You choose whether subs see only their tasks or every step, and whether clients see select milestones or the full schedule.

The catch: critical path isn’t mentioned. Baseline comparison is listed as an “Advanced” feature, and the pricing page doesn’t say which plan includes it. Pro is $199 a month for one user, Teams starts at $399 for 5 users, and extra users are $50 each. After the 30-day free trial an annual subscription begins.

Fieldwire: lookahead planning, with a free plan

Fieldwire by Hilti offers Kanban, Gantt and calendar views, pull planning and three-week lookahead sessions, spreadsheet import, and “related tasks” that flag conflicts between trades. You can dispatch work to each specialty contractor and foreman, on iPhone, iPad and Android.

The catch: Fieldwire’s scheduling page calls it “free construction scheduling software” and shows Gantt, but the pricing grid doesn’t list Gantt by plan, and dependencies and baselines aren’t described. Basic is free for 5 users, 3 projects and 100 sheets. Pro is $39, Business $64 and Business Plus $89 per user a month billed annually (November 20, 2026).

Microsoft Planner and Project: the classic scheduler, with Project desktop in Plan 3

Microsoft Project, the best-known of the construction scheduling programs, now comes with Microsoft’s Planner plans (Microsoft still lists Project separately for advanced project management). Planner Plan 1 ($10 per user a month, paid yearly) adds finish-to-start dependencies, a Timeline (Gantt) view, milestones and a People view for balancing workload. Planner and Project Plan 3 ($30) adds baselines, critical path, lead and lag, and the Project desktop app on up to 5 PCs per user.

The catch: it’s a general scheduler with no sub or client portal, daily logs or job costing. The annual subscription auto-renews; the one-month trial needs a card.

Smartsheet and monday.com: general Gantt tools

Smartsheet includes Gantt, calendar, dependencies and mobile apps on every plan. Pro is $9 per member a month billed yearly ($12 monthly) for up to 10 members, with unlimited free contributors. Baselines need Business ($19 yearly, 3-member minimum). monday.com puts Timeline and Gantt views on Standard ($12 per seat a month, billed annually) and task dependencies on Pro ($19). Plans start at 3 seats.

The catch: neither is built for construction: no crew board, client portal or job costing.

Connecteam and Crew Console: crew schedulers, not project schedulers

Connecteam is free for up to 10 users. Teams of 11 to 29 can stay free on its Limited plan, which allows a single schedule; otherwise Basic is $29 a month for the first 30 users, billed yearly. Repeating shifts and templates start on Advanced ($49), and auto-assign on Expert ($99). Crew Console schedules jobs, crews and equipment in the browser for $7 per person a month, or $10 with time-keeping and job tracking. Neither describes a Gantt chart or dependencies. We compare crew schedulers in depth on our contractor scheduling software page.

Free construction scheduling software: what you actually get

  • Fieldwire Basic: free for 5 users, 3 projects and 100 sheets. The closest free construction scheduler. Fieldwire’s scheduling page calls it free construction scheduling software and shows Gantt, but the pricing grid doesn’t list Gantt by plan.
  • Connecteam Small Business: free for up to 10 users. Its Limited plan is also free for teams of fewer than 30, with a single schedule. Crew and shift scheduling only; no Gantt.
  • Planner in Microsoft 365: included if you already pay for Microsoft 365. It lets you view task dependencies; creating them, and the Timeline (Gantt) view, need Plan 1.
  • monday.com Free: up to 2 seats. Gantt needs Standard.
  • Houzz Pro Free Plan: its plan card lists a 3D floor planner, estimates and invoicing, not scheduling. Houzz’s pricing data may allow one project schedule, which we couldn’t confirm, so check before relying on it.
  • Crew Console Free Job Folder: doesn’t list scheduling.
  • A spreadsheet template: free and familiar, but dates don’t shift when a task slips unless you build the formulas, subs get no alerts, and the “current” schedule is whichever copy was emailed last.

Free trials test a real scheduler better: 30 days on Contractor Foreman and Houzz Pro, 30 days on Smartsheet (no card required), one month on Microsoft (card required), 14 days on monday.com and Connecteam.

What construction scheduling software costs for a 3-, 10- and 25-person company

These are list prices per month on annual billing for the cheapest plan that includes the schedule feature named, before tax. “People” means paid logins.

Software (plan)3 people10 people25 people
Smartsheet (Pro to 10 members; Business at 25)$27$90$475
Microsoft Planner Plan 1 (Gantt, dependencies)$30$100$250
Microsoft Planner and Project Plan 3 (adds baselines, critical path)$90$300$750
monday.com Pro (dependencies)$57$190$475
Contractor Foreman (Plus, then Pro, then Unlimited)$166$221$332
JobTread ($159 + tiered users)$191$303$463
Fieldwire Pro (confirm Gantt is on the plan)$117 ($0 on Basic)$390$975
Houzz Pro (Pro, then Teams + $50/user)$299$649$1,399
Autodesk Forma Build ($117/user)$351$1,170$2,925
Projul (Core+ for Gantt; Pro above 20 users)$599$599$1,199
Procore, BuildertrendQuoteQuoteQuote

JobTread adds $16 per user for users 2–10, $12 for 11–20 and $8 for 21–30. Houzz Teams is “starting at” $399 for 5 users. For crew-only scheduling, Connecteam is $0 at 3 or 10 people; at 25 it’s $0 on the Limited plan (one schedule, fewer features) or $29 on Basic. Crew Console is $21, $70 and $175.

The general tools look cheapest but don’t include estimates, change orders, sub portals or job costing. Contractor Foreman and JobTread do.

How to build a construction schedule

  1. Start from the scope or estimate. Break the job into phases and tasks, or use a template; most construction project scheduling software includes them. Houzz Pro turns estimates into schedules; Projul clones past ones.
  2. Set durations, including inspections and material lead times.
  3. Link dependencies so a slip in one task pushes the ones that follow it.
  4. Assign crews and subs to each task, and turn on their notifications.
  5. Save a baseline, if your tool has one, before work starts.
  6. Update weekly and share a two- or three-week lookahead with the field.

How to evaluate construction scheduling software

  • Check the plan, not the feature page. Projul’s Gantt and Contractor Foreman’s Scheduling both sit above the entry plan.
  • Test a real job during the trial: move one task and see whether everything after it shifts.
  • Count logins. JobTread’s sub and client portals are free and Procore includes unlimited users, while per-user tools charge for each seat.
  • See what subs and clients get: their tasks, a phase, or everything.
  • Check import and export. Procore, Contractor Foreman and Forma Build name MS Project; Procore and Forma Build also name P6.
  • Try the phone app in the field. JobTread is a web app; Buildertrend lists an offline mode.
  • Ask whether the schedule connects to the budget. Buildertrend updates the schedule from change orders, and Forma Build links it to cost.

Who should pick what

  • Remodeler or small residential GC: Contractor Foreman Plus for a full schedule inside a construction suite at a flat price (Microsoft Plan 3 costs less below 6 users if you only need the schedule); JobTread if free sub and client logins matter more; Houzz Pro for design-build. See also our project management software for general contractors.
  • Residential builder with 5+ projects a year: get a Buildertrend quote and price Contractor Foreman Pro or Unlimited against it.
  • Commercial GC with a P6 or MS Project master schedule: Procore, or Autodesk Forma Build if you want a published per-user price.
  • Specialty sub working on GCs’ jobs: Fieldwire for lookaheads and trade coordination; start on the free plan.
  • Office scheduler who only needs a Gantt chart: Microsoft Planner Plan 1 or Smartsheet Pro; Plan 3 for critical path.
  • Crew-only shop or service trade: Connecteam or Crew Console, or a field service tool from the contractor scheduling guide linked above.

What we could not verify

  • Which Fieldwire plan includes Gantt, and whether it supports dependencies.
  • Which Autodesk Forma Build tier includes Schedule, and whether you can build schedules in it rather than import them.
  • Whether Procore’s schedule has its own mobile app view; its schedule page doesn’t say.
  • monday.com’s per-seat prices on monthly billing.
  • Whether JobTread supports dependencies or critical path.
  • Which Houzz Pro plan includes baseline comparison (listed as “Advanced”), and whether the free plan allows a project schedule.

Construction scheduling software: common questions

What is construction scheduling software?

Construction scheduling software plans a job’s tasks, durations and dependencies on a Gantt chart, shows the critical path that drives the finish date, and shares the schedule with crews, subs and clients so dates update when something slips.

What is the best construction scheduling software?

Among construction-specific tools that build the schedule in the app, Contractor Foreman Plus is the lowest published price for Gantt, dependencies, critical path and baselines ($166 a month billed annually, up to 8 users). Microsoft Planner and Project Plan 3 has the same schedule features for less below 6 users ($30 per user a month, paid yearly), but no sub portal, daily logs or job costing. Buildertrend lists a full scheduler plus weather overlays and offline mode but quotes its price. Commercial GCs look at Procore or Autodesk Forma Build.

Is there free construction scheduling software?

Fieldwire Basic is free for 5 users and 3 projects; Fieldwire calls its scheduler free and shows Gantt, but its pricing grid doesn’t list Gantt by plan. Connecteam is free for 10 users (and on its Limited plan for teams of fewer than 30) but only schedules crews. Planner comes with Microsoft 365, but its Gantt view needs Plan 1.

How much does construction scheduling software cost?

On annual billing, general Gantt tools start at $9 to $12 per user a month. Construction tools range from Fieldwire’s free Basic plan and $39 per user a month (Pro) to flat team plans such as JobTread ($159 a month, one user) and Contractor Foreman Plus ($166 a month, up to 8 users). Procore and Buildertrend quote their prices.

Is there a construction scheduling app for my phone?

Yes. Contractor Foreman, Projul, Fieldwire, Smartsheet and monday.com list iOS and Android apps (Projul’s full mobile app starts on Core), and Buildertrend lists an offline mode. JobTread runs as a web app in your phone’s browser, as does Crew Console.

Can I use Microsoft Project or Excel for construction scheduling?

Yes. Microsoft’s Plan 3 ($30 per user a month, paid yearly) has baselines and critical path, and Procore, Contractor Foreman and Autodesk Forma Build import MS Project files. Excel works for simple jobs but won’t shift dates unless you build the formulas, and can’t alert subs.

What’s the difference between construction scheduling and crew scheduling software?

Construction scheduling plans a whole job with a Gantt chart and dependencies. Crew scheduling assigns people to jobs or shifts each day. Projul and JobTread do some of both.

Can scheduling software help with the budget?

Some can. Forma Build links the schedule to cost and Buildertrend updates it from change orders. Smartsheet and monday.com don’t include job costing.

Sources

Vendor pages read November 22, 2026: Contractor Foreman plans and scheduling; Buildertrend schedule and pricing; Procore schedule, pricing and scheduling support; Autodesk Forma Build schedule tool and help; Projul pricing and scheduling; JobTread pricing, scheduling and mobile app; Houzz Pro pricing and scheduling; Fieldwire scheduling; Microsoft Planner plans; Smartsheet pricing and help center; monday.com, Connecteam and Crew Console pricing. Forma Build and Fieldwire prices were read from their pricing pages on November 20, 2026.

Prices are the vendors’ own published list prices on the dates shown, before tax. Vendors change prices often, so check the current page before you buy. For dated prices on every vendor we track, see the contractor software pricing tracker.

Disclosure: Augmented Trades participates in affiliate programs and may earn a commission if you sign up through some links in this article (Projul and Contractor Foreman), at no extra cost to you. Procore, Autodesk, Buildertrend, JobTread, Houzz Pro, Fieldwire, Microsoft, Smartsheet, monday.com, Connecteam and Crew Console are not affiliates. Full details: affiliate disclosure.

Not sure which tools fit your shop?

Answer a few quick questions and our free Tool Finder builds you a custom software shortlist — with the reasoning and pricing behind each pick.

Find your tools (free) →
Written by Michael

Michael is the founder of Augmented Trades, an independent site that compares AI and software tools for trade contractors on published pricing, contracts, and real feature limits. Tools are recommended on fit for your shop — affiliate partnerships never decide coverage.