Short answer: this free construction schedule template is a Gantt-style Excel and Google Sheets file built for residential and trade jobs. Enter a start date and each task’s workdays, link it to the task that has to finish first, and the end dates and weekly bars fill in on their own. It comes pre-filled for a kitchen remodel, a small new home and a roof replacement, with the inspections already in the sequence, plus a 3-week look-ahead and a printable PDF.

Download the PDF (free, print and fill) →
What you get
- Printable PDF: 12-week Gantt grid, 3-week look-ahead sheet and typical job sequences with inspection points
- Excel / Google Sheets schedule: dates and Gantt bars calculate from your start date, pre-filled for a remodel, a new home and a roof replacement
- The Free Contractor Forms Pack: editable files for this schedule plus the new work order, construction contract, punch list, subcontractor agreement, daily report, HVAC maintenance checklist and HVAC service agreement templates
Want the editable Excel schedule? Enter your email at checkout and download the Free Contractor Forms Pack instantly, free, no card.
Tick the newsletter box at checkout and we will send you new contractor templates as we publish them. It is optional.
What a construction schedule is for
A construction project schedule lists every task on the job in the order it has to happen, who does it, how long it takes and when it starts and ends. On a small job it does three things. It tells each sub when to show up. It tells you when to book inspections and order long-lead materials. And it gives the client a finish date you can defend when something slips.
Most free templates give you a blank Gantt chart or a commercial example. This one starts from the jobs residential contractors actually run, so you edit a realistic sequence instead of typing one from scratch.
What’s in the construction schedule template
The Excel file has six tabs: Remodel, New Build, Roof Replacement, 3-Week Look-Ahead, Days Off and How to use. It has no macros, so it opens the same way in Excel and Google Sheets. Each schedule tab has these columns:
- ID: a fixed number for each row. Other tasks point at it.
- Phase: pre-construction, demo, rough-in, close-in, finishes, trim-out, closeout (or foundation, framing and dry-in on the new build).
- Task and Trade / sub: what gets done and who does it.
- Pred. ID: the task that must finish before this one starts.
- Lag: extra workdays to wait after the predecessor, such as concrete cure time or the wait for an inspector. A negative lag lets two tasks overlap.
- Fixed start: optional. Type a date when something is locked in, like a crane or a delivery.
- Start, Workdays and End: start and end calculate with the WORKDAY function, so weekends and your Days Off list are skipped. Zero workdays makes a milestone.
- % done and Status: Not started, In progress, Done, Delayed or On hold, picked from a drop-down.
- Type: Task, Inspection, Milestone or Lead time. Inspections get their own bar color, so you can see them at a glance.
- Next 3 wks: says Yes when the task falls in the next three weeks. Filter on it to build your look-ahead.
- Gantt area: weekly columns on the remodel and new build tabs and daily columns on the roof tab. Bars are orange for work, dark for inspections, brown for milestones, grey when 100% done and red when delayed. The current week (or day, on the roof tab) is shaded.
The top of each tab shows the project start, the calculated finish date, total workdays, overall percent complete (weighted by workdays), the number of inspections and the number of delayed tasks.
The PDF is for crews who work on paper or for a wall in the job trailer. Page 1 is a blank 26-row, 12-week Gantt grid with day ticks. Page 2 is a blank 3-week look-ahead. Page 3 lists the typical sequence for all three job types with the inspection points marked.
Three pre-filled construction project schedules
- Kitchen remodel (26 tasks): selections, cabinet lead time and permit, then demo, rough-in, a rough inspection, insulation, drywall, paint, flooring, cabinets, countertop template, fabrication and install, backsplash, trim-out, a final inspection and sign-off.
- Small new home (34 tasks): permit, survey, site work, footing and foundation inspections, framing, dry-in, rough-ins, framing and rough-in inspections, an insulation inspection, drywall, exterior, interior finishes, final inspections, certificate of occupancy and handover.
- Roof replacement (16 tasks, daily view): measurements, permit, material order, dumpster, tear-off, decking repairs on the same day, a deck or ice-barrier inspection where your city requires one, underlayment, shingles, flashing, cleanup, a final inspection and paperwork.
Inspection names and timing vary by city and county. Some areas skip an insulation inspection, and some want a mid-roof check. Use the sequence as a starting point and match it to the permit card for your job.
Filled-in example: kitchen remodel
Here is part of the Remodel tab with a start date of Monday, March 1, 2027 and the example holidays on the Days Off tab. The durations are illustrative, not a promise of how long any job takes.
| ID | Task | Trade | Pred. | Workdays | Start | End |
|---|---|---|---|---|---|---|
| 1 | Contract signed, deposit received | Office | – | 1 | Mon Mar 1 | Mon Mar 1 |
| 3 | Cabinet lead time (order to delivery) | Supplier | 2 | 30 | Tue Mar 9 | Mon Apr 19 |
| 4 | Permit application and approval | Office | 1 | 15 | Tue Mar 2 | Mon Mar 22 |
| 6 | Demo kitchen to studs | Demo crew | 5 | 3 | Wed Mar 24 | Fri Mar 26 |
| 9 | Rough electrical | Electrician | 7 | 3 | Wed Mar 31 | Fri Apr 2 |
| 11 | Rough inspection (lag 2) | Inspector | 9 | 1 | Wed Apr 7 | Wed Apr 7 |
| 13 | Drywall: hang, tape, finish | Drywall sub | 12 | 6 | Fri Apr 9 | Fri Apr 16 |
| 16 | Install cabinets | Carpenter | 15 | 3 | Tue Apr 27 | Thu Apr 29 |
| 18 | Countertop fabrication | Fabricator | 17 | 8 | Mon May 3 | Wed May 12 |
| 24 | Final inspection (lag 2) | Inspector | 23 | 1 | Mon May 24 | Mon May 24 |
| 26 | Walkthrough and sign-off | Owner + client | 25 | 0 | Thu May 27 | Thu May 27 |
Two things to notice. The cabinets arrive on April 19, eight days before the install, so the long-lead item is not on the critical path. And the rough inspection has a two-day lag, because you rarely get the inspector the day after you call. If the drywall sub loses two days, change that row and every task after it moves.
How to use the template, step by step
- Pick the closest tab and duplicate it for your job. Keep the original as a clean copy.
- Fill in the header: your company, the project, client and job site.
- Set the project start date in cell H3. Every date on the tab calculates from it.
- Edit the Days Off tab. Delete the example holidays your crews work and add your own.
- Rewrite the tasks in your own order and words. Enter the workdays from your own past jobs and your subs’ estimates.
- Link each task to the one that must finish first. The predecessor has to sit higher in the list. If a task waits on two others, point it at the one that ends last.
- Add lag for cure times and inspection waits, and mark each inspection as Type = Inspection.
- Send the schedule to the client and subs as a PDF. Use File > Print in Excel or File > Download > PDF in Google Sheets. Each tab prints landscape, one page wide.
- Update it every week. Set % done and Status, add rain days to Days Off, and send the new finish date to the client.
The 3-week look-ahead
The master schedule shows the whole job. The look-ahead shows what is happening in the next 15 workdays, one day at a time. Each week, filter a schedule tab’s Next 3 wks column to Yes and copy those tasks across. Mark each day X for crew working, I for an inspection or D for a delivery. Then fill in what each task needs before it can start and whether it is ready.
The Ready column is the useful part. A task marked No (cabinets not confirmed, colors not signed off, material not on site) gets a name and a date before you book the crew. Review the sheet with your subs before you commit them. If you also keep a construction daily report, its delays and notes are what you use to update the look-ahead each week.
Scheduling rules that protect your margin
- Order long-lead items the week the contract is signed. Cabinets, windows, trusses and special-order materials set the real finish date. Put them in as Lead time rows so you see them.
- Book inspections when the work before them starts, not when it ends. The lag column is there because waiting on an inspector is a normal part of the job.
- Schedule in workdays, not calendar days. A five-day task that starts on a Thursday ends the next Wednesday. The WORKDAY formula handles it.
- Don’t give the client the tightest date. Give the finish date from the schedule and say which items could move it, such as weather, selections and inspections.
- Log every slip the day it happens. Add rain days to Days Off and mark tasks Delayed. A schedule you update once a month can’t help you.
- Tie scope changes to the schedule. When a change order adds days, add them here and put the new completion date on the change order.
When a spreadsheet schedule stops working
A spreadsheet works well for one or two jobs at a time and one predecessor per task. It starts to break down when tasks wait on several others, when the same crew is booked on three jobs in the same week, or when subs and clients need updates the moment a date moves. At that point you are copying dates between files and texting screenshots. If the crew calendar breaks first, an employee scheduling app for construction is the cheaper fix.
Construction scheduling software fixes those three problems. Projul has a drag-and-drop Gantt view where dependent tasks shift when a predecessor slips, crew and sub assignment, and phone notifications when dates change (from Projul’s scheduling page, read November 25, 2026). Buildertrend‘s schedule adds baselines to compare against the original plan and a client portal view of the timeline (from Buildertrend’s schedule page, read November 25, 2026). For a side-by-side comparison, see our guide to construction scheduling software. If your problem is dispatching crews to many small jobs rather than sequencing one long project, start with scheduling software for contractors. If you also need budgets, change orders and client updates in one place, see project management software for general contractors.
Construction schedule template: common questions
Is this construction schedule template free?
Yes. The PDF downloads directly from this page. The editable Excel file is free too, with an email at checkout, as part of the Free Contractor Forms Pack.
Does the construction schedule template work in Google Sheets?
Yes. Upload the .xlsx file to Google Drive and open it with Google Sheets. The formulas, drop-downs and Gantt colors use only standard functions and conditional formatting, with no macros.
How do the Gantt bars update?
Each bar is conditional formatting that compares the task’s start and end dates to the date at the top of each column. Change the project start date, a duration, a predecessor or a day off, and the dates and bars redraw.
Can a task have more than one predecessor?
Not in this template. Point the task at the predecessor that finishes last, or type a fixed start date. If you need several links per task, that is the point where scheduling software is worth it.
How do I add rain days or holidays?
Add the date to the Days Off tab. All three schedules skip it, and every task after it moves out by a day.
Are the inspections in the template required where I work?
They are common examples, not a legal list. Inspection names, timing and which ones are required vary by city and county. Check the permit card or the building department for your job.
More free contractor templates
- Construction daily report template
- Punch list template
- Work order template
- Construction contract template
- Subcontractor agreement template
- Change order template
- Contractor estimate template
- Free contractor invoice template
- HVAC maintenance checklist
- HVAC service agreement template
Templates are free to use and edit for your own business. Example tasks and durations in the spreadsheet are illustrative, not a promise of how long any job takes. Some links on this page are affiliate links; see our affiliate disclosure.